Moira Court

Scaffolding is now complete at Moira Court, with the site ready for works to begin. Investigation and scheduling are currently taking place, with works progressing subject to approval. The project will include: Extensive masonry repairs, including replacement rendering General roof repairs, including new leadwork capping to the parapet walls Extension of the handrails to the…

Flat 1, 69 Holland Park

We continue to build on our portfolio of properties within the Holland Park area and commenced works this morning to rectify water damage to a basement bathroom, following a leak from the property above. The works will include: • Electrical testing of all existing cabling. • Strip-out and removal of damaged units and sanitaryware as…

Egerton Court

Collins commenced works on site today at Egerton Court. This prominent block sits on the corner of Old Brompton Road, directly opposite South Kensington Tube Station. As a result of its prime location and high levels of visibility, the client has taken the opportunity to introduce a bespoke scaffold advertising wrap in partnership with Rolex,…

Medway Valley Park

Collins have completed the remedial internal works at this unit within Medway Valley Park. Working within a busy, fully operational warehouse presented additional logistical and safety considerations. To minimise disruption and reduce interaction between our team, warehouse operations and site traffic, the works were scheduled to take place outside the warehouse’s busiest periods, when vehicle…

2-8 Hyde Park Gardens

Collins are progressing well with the final stages of works at 2-8 Hyde Park Gardens. This final phase includes damp-proofing to two flats using a guaranteed system, together with all necessary enabling and making-good works. To three terraces, we have removed the existing patio finishes and are installing Langley liquid waterproofing systems following reports of…

Bickenhall Mansions

Blocks 3 & 5 at Bickenhall Mansions are now coming to a close; we have begun striking the scaffold, working our way down the building signing off all works undertaken including the roofing, masonry, timber repairs, decorating, window replacement, rainwater good replacements & railing repairs. We will then be finalising any left-over repairs within the…

Knott House

Scaffolding is progressing well on site at Knott House, with the team making excellent progress. Due to the nature of the building and its surrounding environment, the scaffold has required detailed planning and coordination to work safely around pedestrian areas, while also following the curvature of the building perimeter and maintaining the required configuration in…

44 Pont Street

Works are progressing well here at 44 Pont Street. We are actively progressing with 1st fix trades, including plumbing and electrical works, followed by the closure of all pipework and cabling with new ceilings and plastering, in accordance with the clients proposed layouts. We are now actively undertaking the floor-levelling works and commencing the second-fix…

Financial Conduct Authority

Our 20-week internal redecoration project at the Financial Conduct Authority offices in Stratford is progressing well as we work towards completing the project. We have now handed over Levels 15 , 11, 10, 9, 8, 3, 2,1, along with all stair cores and the Mezzanine floor. This project is being delivered safely and efficiently out of…

27–30 Lime Street

Having successfully completed the external repairs and maintenance programme at 27–30 Lime Street in April last year, we are pleased to have been invited back to undertake a 10-week CAT A & B refurbishment programme to the fourth floor. Working within this Grade II Listed building, the refurbishment will carefully balance the requirements of a…