All scaffold is now coming down following various works including, masonry and timber repairs / external decorations / internal secondary glazing / gutter lining (delcote) / flat roof liquid works (Langley) / full window overhauls including new fixtures and fitting / new lead works.
Spire works – new glazing / decorations / masonry repairs and pointing.
The remaining works are to be carried out to the rear elevation of a new glazed walkway enclosure.
Look out for further updates coming soon.