Phase 2 of the external refurbishment and redecorations project is progressing well, to this period property located in West Hampstead.
Project update:
- The main roof underwent structural improvements and re-roofing works
- Lead is currently being added to the dormer cheeks
- 2no lifts are now fully complete in regards to the Masonry & brickwork
- Another lift has now been released to us and is 100% cut out ready for repairs
- The external redecorations have also now begun
Look out for updates as works progress throughout this 20 week project.