Works have just begun to this commercial office building in Moorgate. We are carrying out the internal refurbishment works to the following areas –
· WC refurbishment Lower Ground-6th floor
· External entrance to be stripped out and re clad in Portland stone
· New reception and ground floor entrance
· Lift refurbishment
· Upgraded lighting throughout
This 28 week project is due for completion at the end of the year.
For progress information on this project, watch out for updates and photographs on our news feed.